General Plan Amendment

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The City’s General Plan is the principal set of goals and policies guiding future growth and development of the City. Proposed changes to the General Plan require an application for a General Plan Amendment. Questions related to the City’s General Plan or a proposed General Plan Amendment can be answered by a Planner in the City’s Community & Economic Development Department.

Step 1 Submit Application
Development application forms and general submittal requirements are available on the City’s website and at the front counter of the Community & Economic Development Department. A City Planner will assist you through the process.
Step 2 City Council Approval of a Cost Recovery Agreement
To initiate the application process for a General Plan Amendment, a Cost Recovery Agreement is required. This provides a mechanism for the City to recover the applicable City staff and consultant costs associated with the application, which vary depending on the scope and complexity of the project.
60 days (typical)
Step 3 City Review
City review includes routing application materials to multiple City departments and other agencies for comments. The comments are compiled into a comprehensive letter to the applicant, which details staff recommendations, including the likely environmental review process and information related to zoning that may be affected by the General Plan Amendment. Once the application requirements are met, including environmental review, City staff will prepare the project for public hearing (steps 6 and 7).
30 days
Step 4 Applicant Response
Some projects require additional information or clarification by the applicant and/or revisions to the plans. This step is the applicant’s response to those requirements. The applicant’s response will be reviewed by the City and steps 3 and 4 may be repeated if necessary.
30 days (typical)
Step 5 Preparation of CEQA Document
General Plan Amendments are subject to environmental review in accordance with the requirements of the California Environmental Quality Act (CEQA). A City Planner will assist you in understanding the requirements of CEQA.
90 days – 18 months (typical)
Step 6 Planning Commission – Public Hearing
General Plan Amendments require public hearings with both Planning Commission and City Council (step 7).
30 days (typical)
Step 7 City Council – Public Hearing
General Plan Amendments require public hearings with both Planning Commission (step 6) and City Council.
30 days (typical)
Estimated Total Timeframe 9 months – 2 yrs (typical)*

*General Plan Amendments are typically associated with complex projects, processed concurrently with other applications.


Resources

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer